Driven past it a hundred times, but never really noticed it: the Migros distribution centre in Münchenstein. We were able to get a glimpse behind the scenes during our last project.

In cooperation with Jean Cron AG, Tozzo AG and Schenk AG, we were able to lay three new trenchless sewer lines. The rainwater is now collected along the building via gutters and drained to the sewer system below the floor slab. Since the basement is offset from the upper floor, only a trenchless method was possible to make the connection. With the help of the flush drilling method, we were able to pull in a DN200 pipe three times under the distribution centre.


More Photos & Videos on Instagram.