top of page
S+M Tiefbau provides you with clean and fair civil engineering services at a high quality level. We work in close cooperation with local authorities, such as the Liestal waterworks, EBL, Primeo, IWB, Nuglar municipality and so on.
Efficient and accurate work is only possible with clean and functional equipment. All our vehicles and machines are serviced periodically and are ready for use at any time.
​
In addition to the services listed below, we also serve private customers. Be it a new construction of a single-family house, the redesign of the forecourt or repair work on natural stones and concrete products. We are available for all kinds of projects.
civil work
road work
tarmac
excavation
paving
Finished repairs | Install reinforcing bars | |
---|---|---|
Removing the concrete chunks | Damaged post | Excavation work for a new street light |
Exposing the electrical cable | Setting the shaft and connecting the electrical lines | |
Casting the shaft in concrete | Fill and... | |
compact the slope | Treat surface and clean up th site | Location for new electrical distribution box defined |
Demolition of the concrete wall | Create formwork | Install reinforcement mesh to strengthen the wall |
Securing the formwork and filling in the liquid concrete | ||
Remove formwork and carry out the finishing work | Create base plate with infiltration connection | |
Install distribution box | Laying the protective pipes to the box | |
Finished repair work around the distribution box | ||
Laying ashlar stones for a new transformer station | Adjustment of the terrain | |
3301-2-1 | Install a privacy screen | |
New gas & water connection | ||
Complex trench protection in the middle of working pipelines | ||
Gas & water pipe laid in trench | Trench filled with gravel material and compacted | |
Finished pavement work | ||
Concrete work for new truck lift | Finished surface | |
Finished truck lift foundation | ||
Installation of the truck lift | Trench excavation for connection lines to the heat pump | |
Concrete foundation for heat pump | Trenchless under the seating area | |
Core drilling and finished installation | Restoration of the garden | |
Installation of the reinforcement grid | New foundation for the car lift | |
Concrete foundation for thermoforming tool | Concrete foundation for thermoforming tool | |
Old gutter... | ... new gutter | |
Pavement construction with different slopes | New transformer station | |
Trench for connection lines | Foundation for transformer station | Transformer station |
Laying the pipes | Water ingress into the cellar | |
Trench excavation and repair of the wall | Laying the seepage line around the house | Casting the seepage line in concrete |
Waterproofing the house wall | Filling up with gravel | Backfill and compacting the trench |
New sewer connection | ||
Pavement construction between the train tracks | ||
Removing old petrol tank | ||
bottom of page